Sunday, April 29, 2007

Construction Update



Lots was accomplished this past week. The floor tile was installed in most of the house. The garage doors were set and the ground was prepared for the concrete drives.

Next week we'll see a lot of changes. Tile work will continue, including the showers and master bath, the cabinets should be installed and we will pour the concrete drives.

The weather has been wonderful, and we're hoping for more this next week.

Monday, April 23, 2007

Darin & Katie Visit








This past week we were fortunate to have Darin and Katie visit with us here in Heber Valley. Mike has already begun is work at Countrywide, so he wasn't able to join them on the trip. After their move to California, we've missed them. So having them here was quite a treat.


Activities included several trips to the park, walks with Katie and dinner at our friend's cabin in Woodland, UT.


Construction Update




This past week, most work was completed on the outside of the house. The facia and soffit were installed, as well as the rain guttering. Today we laid out the driveways and concrete pads. That work should start in a week or two.
Inside, all of the sheetrock texturing is complete and they've begun preparation for laying tile. Actual tile work began today and will continue for two weeks. Hopefully, next week we'll see the cabinets installed and the trim carpentry work should begin.

Saturday, April 7, 2007

Construction Update


We've had beautiful spring weather this past couple of weeks and the masons were able to complete the external brick work on the home.

On Friday, they applied the color coat to the stucco on the house and begin installing the soffit and facia trim to the outside. It is really starting to look like our home.

Inside the second coat of mud is being applied. Texturing will start next week. Two more weeks and we should be ready for cabinets, tile work and trim work.

Lots of fun, here.